The Maximum Number of Weeks for Which You Can Work coding problem gives you an array milestones, where milestones[i] represents the number of weeks required to complete the i-th project. You can work on any project at any time, but you cannot work on the same project for two consecutive weeks. You want to find the maximum number of weeks you can work across all projects.
Wells Fargo, SAP, and Natwest use this problem to test greedy algorithms, especially those involving sorting and critical element identification. It's a game-theory type problem where maximizing the total work weeks often comes down to strategically using the project with the most remaining work.
Greedy Approach with Maximizing Critical Resource:
The constraint "cannot work on the same project for two consecutive weeks" is key. This means if you work on project A this week, you must work on a different project next week. If project A has an extremely high number of weeks, it becomes a "bottleneck" or "critical project".
The greedy strategy:
max_milestone_weeks.sum_other_weeks.max_milestone_weeks <= sum_other_weeks + 1: You can always interleave the max_milestone_weeks project with weeks from other projects. The +1 allows for the last week of max_milestone_weeks to be worked on without needing an "other" project to separate it from itself. In this scenario, you can work for total_sum_of_all_milestones weeks.
b. If max_milestone_weeks > sum_other_weeks + 1: The max_milestone_weeks project is too dominant. You will exhaust all other projects, and then you'll be forced to work on max_milestone_weeks twice in a row, which is forbidden. In this case, you can work sum_other_weeks weeks from other projects, and sum_other_weeks + 1 weeks from the max_milestone_weeks project (interleaving sum_other_weeks of its weeks with sum_other_weeks from other projects, and then one more week from it). So, the total work weeks will be 2 * sum_other_weeks + 1.Total sum = max_milestone_weeks + sum_other_weeks.
So, if max_milestone_weeks > sum_other_weeks + 1, the answer is 2 * sum_other_weeks + 1.
Otherwise, the answer is total_sum_of_all_milestones.
milestones = [1, 2, 3].
max_milestone_weeks = 3 (from project with 3 weeks).sum_other_weeks = 1 + 2 = 3.max_milestone_weeks (3) vs sum_other_weeks + 1 (3 + 1 = 4).
Since 3 <= 4, it falls into case (a).
Total work weeks = total_sum_of_all_milestones = 1 + 2 + 3 = 6.
(Example interleaving: P3, P1, P3, P2, P3, P? (P2 is done, P1 is done) - Wait, P3, P1, P3, P2, P3, P2. That's 6 weeks. P3 (1), P1(1), P3(2), P2(1), P3(3), P2(2). All done. )milestones = [1, 100].
max_milestone_weeks = 100.sum_other_weeks = 1.max_milestone_weeks (100) vs sum_other_weeks + 1 (1 + 1 = 2).
Since 100 > 2, it falls into case (b).
Total work weeks = 2 * sum_other_weeks + 1 = 2 * 1 + 1 = 3.
(Example interleaving: P100, P1, P100. P1 is done. P100 needs 98 more. But can't work P100 again. So, total 3 weeks.)+1 in sum_other_weeks + 1 is critical for the boundary condition where the max project can perfectly interleave.2 * sum_other_weeks + 1 is the limit when| Title | Difficulty | Topics | LeetCode |
|---|---|---|---|
| Decrease Elements To Make Array Zigzag | Medium | Solve | |
| Gas Station | Medium | Solve | |
| Increasing Triplet Subsequence | Medium | Solve | |
| Largest Element in an Array after Merge Operations | Medium | Solve | |
| Maximize Score After Pair Deletions | Medium | Solve |